This is the latest in a series of blogs from West Virginia Student Reporter Abbey Hart on behalf of Bobby Lewis, State Director
On November 16, 2010, a Construction Progress Meeting was held at the Newburg Town Hall. Although progress has been slower this past month, 76 percent of the project is finished. With the exception of 3200 feet of waterline, all of Route 26 is complete. Also, approximately 50 percent of the new waterline has been pressure tested.